Project configuration
1 · Processing capacity
2 · Ownership structure
Structuring allowance only. Shareholding, investment eligibility and land rights require Tanzanian legal review.
3 · Land & site
4 · Electricity & resilience
5 · Processing machinery
6 · Working capital
Inventory is calculated from selected capacity, operating days, RCN price and coverage; buffer is added for payroll, packaging and cash operating needs.
7 · Optional facilities
All figures are indicative USD allowances, not quotations.
Live investment estimate · Segment-wise costing
Selected capacity2 MT/day
Machinery allowance$53,570
Working capital—
CURRENT CONFIGURATION · ESTIMATED PROJECT FUNDING
—
Updating from selected options…
Cost segments
Low–high estimate · tap “cost details”Estimated funding total
Includes contingency & working capital
Includes contingency & working capital
—
Scenario presets
Indicative implementation sequence
Month 1Structure, site shortlist, feasibility
Months 1–3Approvals, site lease & civil works
Months 2–4Machinery production & checks
Months 4–6Shipping, installation, utilities
Months 5–7Training & trial processing
Months 6–8Ramp-up (schedule dependent)
Costing basis: Oscar Cashew Tech's quotation for a 2,000 kg/day RCN input fully automatic line is $53,570 Ex-Works Ahmedabad. Other segment values are budget allowances. Quotation exclusions include civil work, electrical lines, boiler water line, humidifier room, freight and buyer-paid engineer travel/lodging. This calculator does not treat the quotation as a delivered factory cost. Actual costs, taxes, licence requirements, land arrangements, freight and installation will vary and must be confirmed.
Planning model only · No land, licence, import approval, incentive, or production output is assumed to be guaranteed.